Scope of Work:
* Level 2 ASP Electrical Works: Upgrade the overhead service mains from the network service pole to the private power pole, including associated service connections.
* Complete Switchboard Upgrade: Remove and replace the existing main switchboard with a new switchboard, including new circuit breakers, RCBOs, main switches and associated wiring.
* Sigenergy Battery Installation: Install and commission a Sigenergy battery energy storage system.
* Sigenergy Gateway Installation: Install and configure the Sigenergy Gateway to provide automatic backup power during grid outages.
* Testing & Commissioning: Carry out all necessary electrical testing, safety inspections and system commissioning to ensure compliance with relevant Australian Standards.
Jean St Seven Hills
Project details
Scope of Work:
* Three-Phase Switchboard Upgrade: Upgrade and replace the existing three-phase main switchboard, including associated internal wiring and electrical components.
* Consumer Mains Replacement: Replace the existing consumer mains cables with new appropriately sized cables to meet current electrical standards and requirements.
* Circuit Breaker Upgrades: Replace all existing circuit breakers (CBs) with new protective devices, including RCBOs where required, to improve electrical safety and protection.
* Testing & Commissioning: Complete all necessary electrical testing, inspections and commissioning in accordance with relevant Australian Standards.
Bromley Ave Pymble
Project details
Scope of Work:
1. Private Power Pole Replacement
* Remove and replace the existing leaning private power pole with a new compliant pole to ensure structural stability and electrical safety.
2. Main Switchboard Upgrade & Expansion
* Upgrade and enlarge the existing main switchboard due to overcrowded circuit breakers, disorganised internal wiring and insufficient space.
* Install a new, larger switchboard enclosure to provide adequate space for all electrical components, ensure the cover can be securely fitted and allow for future maintenance.
3. Electrical Wiring Reorganisation
* Reorganise and reroute the existing wiring within the switchboard.
* Improve cable management, circuit layout and overall electrical safety.
4. Testing & Commissioning
* Carry out necessary electrical testing, safety inspections and commissioning in accordance with relevant Australian Standards.
Sydney St North Willoughby
Project details
Scope of Work:
1. Overhead Service Damage Assessment & Restoration
* The existing overhead service line was brought down by a falling tree branch, causing significant damage and deformation to the timber mounting board and metal cladding at the Point of Attachment (POA).
* A qualified carpenter was engaged to replace the damaged timber mounting board and repair the affected mounting structure.
2. New Private Power Pole Installation
* The original overhead service route from the network service pole to the existing POA would cross over the neighbouring property’s airspace, which does not meet current clearance and service installation requirements.
* A new private power pole was installed to provide a compliant overhead service connection without crossing the neighbouring property’s airspace.
3. Consumer Mains Replacement
* The existing consumer mains cables were undersized and required upgrading.
* Replaced the existing consumer mains with appropriately sized cables to meet current electrical requirements and ensure safe, reliable power supply.
4. Main Switchboard Relocation & Complete Upgrade
* The original main switchboard was installed at an excessive height above the entrance door on the left-hand side, making it difficult to access and not compliant with current accessibility requirements.
* Relocated the main switchboard to a new, accessible and compliant position.
* Replaced and upgraded the existing switchboard components, including circuit breakers, protective devices and associated internal wiring.
5. Electrical Testing & Commissioning
* Completed necessary electrical testing, safety inspections and commissioning to ensure the installation meets relevant Australian Standards and electrical safety requirements.
Bannockburn Rd Pymble
Project details
Scope of Work:
1. Overhead Service Mains Replacement
* Replace the existing overhead service line crossing the street with a new overhead service connection suitable for the three-phase power supply upgrade.
* Complete all necessary Level 2 ASP service connection works.
2. Consumer Mains Replacement & Three-Phase Upgrade
* Replace the existing undersized consumer mains cables with appropriately sized three-phase cables.
* Upgrade the existing single-phase power supply to a three-phase supply to meet the property’s electrical requirements.
3. Complete Three-Phase Switchboard Upgrade
* Remove and replace the existing main switchboard with a new three-phase switchboard.
* Replace all existing circuit breakers (CBs) with new protective devices, including RCBOs as required.
* Upgrade and reorganise all associated internal wiring, main switches and electrical components to accommodate the new three-phase supply.
4. Sigenergy Battery & Gateway Installation
* Install and commission a Sigenergy battery energy storage system (BESS).
* Install and configure the Sigenergy Gateway to enable automatic backup power during grid outages.
* Integrate the battery and Gateway with the upgraded three-phase electrical system.
5. Testing & Commissioning
* Carry out all necessary electrical testing, inspections and commissioning in accordance with relevant Australian Standards and network service provider requirements.
Graham Ave Pymble
Project details
Scope of Work:
1. Overhead Service Upgrade – Single-Phase to Three-Phase
* Replace and upgrade the existing single-phase overhead service mains crossing the street with new three-phase overhead service mains.
* Replace and upgrade the overhead service line from the network service pole to the property’s Point of Attachment (POA) from single-phase to three-phase.
* Complete all associated Level 2 ASP service connection works.
2. Consumer Mains Replacement
* Replace the existing consumer mains with appropriately sized three-phase cables to accommodate the upgraded three-phase power supply.
* Upgrade and reconnect all associated service wiring as required.
3. Main Switchboard Relocation & Three-Phase Upgrade
* Remove the existing main switchboard and relocate it to a new, more suitable position.
* Install a new three-phase main switchboard with upgraded main switches, protective devices and internal wiring.
* Reorganise and reconnect the existing circuits to accommodate the new three-phase electrical system.
4. Complete RCBO Upgrade & Circuit Relocation
* Remove all existing circuit breakers (CBs) from the original indoor distribution board.
* Upgrade all existing CBs to individual RCBOs, providing both overload/short-circuit protection and residual current protection.
* Relocate and reconnect all existing circuits into the new main switchboard, eliminating the need for the original indoor distribution board.
5. Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and commissioning in accordance with relevant Australian Standards and network service provider requirements.
Pembroke Rd Marsfiled
Project details
Scope of Work:
1. Existing Overhead Service Disconnection
* Disconnect and remove the existing overhead service connection crossing the street to allow for the demolition and rebuilding of the property.
* Carry out all necessary Level 2 ASP disconnection works.
2. Private Power Pole Installation
* Supply and install a new private power pole to establish a suitable power supply connection for the construction site.
3. Overhead Service Reconnection
* Install and reconnect new three-phase overhead service mains from the network service pole to the new private power pole.
* Complete all associated Level 2 ASP connection works.
4. Consumer Mains Installation
* Supply and install new three-phase consumer mains cables from the private power pole to the temporary switchboard.
5. Three-Phase Meter & Temporary Switchboard Installation
* Install a new three-phase electricity meter and temporary construction switchboard.
* Install the required main switch, circuit breakers, RCBOs and associated electrical components.
* Provide a safe and reliable temporary three-phase power supply for demolition and construction activities.
6. Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and commissioning in accordance with relevant Australian Standards and network service provider requirements.
Wellington Rd East Lindfield
Project details
Scope of Work:
1. Private Power Pole Installation
* Supply and install a new private power pole to establish a suitable power supply connection for the construction site.
2. Three-Phase Overhead Service Installation
* Install new three-phase overhead service mains crossing the street from the network service pole to the new private power pole.
* Complete all associated Level 2 ASP overhead service connection works.
3. Consumer Mains Installation
* Supply and install new three-phase consumer mains cables from the private power pole to the temporary construction switchboard.
* Complete all necessary cable connections and associated wiring.
4. Three-Phase Meter & Temporary Switchboard Installation
* Arrange for the installation of a new three-phase electricity meter.
* Supply and install a new temporary construction switchboard and distribution board.
* Install the required main switches, circuit breakers, RCBOs and associated electrical components.
* Establish a safe and reliable temporary three-phase power supply for construction activities.
5. Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and commissioning in accordance with relevant Australian Standards and network service provider requirements.
Sydney Rd Hornsby Heights
Project details
Scope of Work:
1. Complete Main Switchboard Upgrade
* Upgrade and replace the existing main switchboard and distribution board with new electrical components.
* Reorganise and upgrade the internal wiring to accommodate the new solar and battery energy storage system.
* Improve the overall safety, accessibility and reliability of the electrical installation.
2. Complete Circuit Breaker to RCBO Upgrade
* Remove all existing circuit breakers (CBs) from the distribution board.
* Replace all existing CBs with individual RCBOs to provide overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all existing electrical circuits.
3. 19kW Solar PV System Installation
* Supply and install a 19kW solar photovoltaic (PV) system, including solar panels, mounting systems, DC cabling and associated electrical components.
* Complete all necessary solar panel wiring and system connections.
4. FoxESS 15kW Three-Phase Hybrid Inverter Installation
* Supply and install a FoxESS 15kW three-phase hybrid inverter.
* Connect and configure the inverter with the solar PV system and battery storage system.
5. FoxESS 41.74kWh Battery Energy Storage System Installation
* Supply and install a FoxESS 41.74kWh battery energy storage system (BESS).
* Complete all necessary battery connections, system configuration and commissioning.
* Integrate the battery storage system with the FoxESS hybrid inverter to optimise solar energy utilisation and storage.
6. Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and system commissioning in accordance with relevant Australian Standards and network service provider requirements.
Broadway Ultimo
Project details
Scope of Work:
1. Existing Electrical Supply Assessment
* The ground-floor commercial shop and upstairs tenancy were originally connected to the same electricity meter, sharing a single metered power supply.
* Upgrade the existing electrical distribution arrangement to provide separate electricity metering for the upstairs tenancy.
2. Commercial Switchboard Expansion
* Supply and install an additional distribution board for the commercial premises.
* Upgrade and reorganise the associated wiring and electrical components to accommodate the new metering arrangement.
3. New Three-Phase Electricity Meter Installation
* Apply for and arrange a new three-phase electricity meter dedicated to the upstairs tenancy.
* Complete the required electrical installation and metering connections.
* Establish an independent metered electricity supply for the upstairs tenancy, allowing its electricity consumption to be measured and billed separately from the ground-floor shop.
4. Electrical Circuit Separation & Reconfiguration
* Separate and reconfigure the electrical circuits associated with the upstairs tenancy and ground-floor commercial premises.
* Connect the upstairs tenancy’s electrical supply to the new three-phase metering arrangement.
5. Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and commissioning in accordance with relevant Australian Standards and electricity network requirements.
Darling St Balmain East
Project details
Scope of Work:
1. Consumer Mains Replacement
* Remove and replace the existing consumer mains with appropriately sized cables to accommodate the upgraded electrical supply and separate metering arrangements.
* Complete all necessary cable connections and associated electrical works.
2. Main Switchboard Relocation
* Disconnect and remove the existing main switchboard from its original location.
* Relocate and install the main switchboard at a new suitable position to meet current electrical installation requirements.
3. Main Switchboard Upgrade & Reconfiguration
* Upgrade and reconfigure the existing switchboard, including internal wiring, protective devices and associated electrical components.
* Modify the electrical distribution system to accommodate two separate electricity meters for the ground-floor commercial shop and upstairs residential tenancy.
4. Separate Three-Phase & Single-Phase Metering Installation
* Configure and connect a dedicated three-phase electricity meter for the ground-floor commercial shop.
* Configure and connect a separate single-phase electricity meter for the upstairs residential tenancy.
* Separate and reconnect the electrical circuits for both premises, ensuring each tenancy has its own independently metered electricity supply.
* Enable separate electricity consumption monitoring and billing for the two premises.
5. Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and commissioning in accordance with relevant Australian Standards and electricity network requirements.
Babbage Rd Roseville Chase
Project details
Scope of Work:
1. Emergency Electrical Response & Make-Safe
* The existing private power pole had suffered severe corrosion and rust damage, causing the pole to break and collapse onto the roadside.
* Responded to an emergency call-out to assess the damage and electrical safety risks.
* Safely disconnected and isolated the affected electrical supply to eliminate immediate electrical hazards and make the site safe.
2. Private Power Pole Replacement
* Arranged for a new private power pole to be installed the following day.
* Removed and replaced the severely corroded and collapsed pole with a new compliant private power pole.
* Ensured the new pole was securely installed to provide a safe and stable electrical supply connection.
3. Outdoor Switchboard Reinstallation
* Reinstalled and secured the outdoor switchboard onto the new private power pole.
* Reconnected and reorganised the associated electrical wiring and components as required.
4. Power Supply Reconnection & Restoration
* Reconnected the electrical supply following completion of the pole replacement and switchboard installation.
* Restored electricity supply to the residential property.
5. Electrical Testing & Safety Inspection
* Carried out the necessary electrical safety inspections and testing before restoring power.
* Ensured the installation met applicable Australian Standards and electricity network requirements.
Adina St Miranda
Project details
Scope of Work:
1. Ausgrid Defect Report & Safety Assessment
* The property owner received a defect notice from Ausgrid regarding serious safety concerns at the existing Point of Attachment (POA).
* The timber mounting board at the POA was severely deteriorated and rotten, while the adjacent metal guttering was heavily corroded and rusted.
* These defects compromised the structural integrity of the overhead service attachment and posed significant electrical safety risks.
2. Level 2 ASP Service Disconnection & Make-Safe
* Attended the property to assess the reported defects and associated electrical hazards.
* Safely disconnected and isolated the existing overhead electrical service to allow the necessary structural repairs to be carried out.
* Made the electrical installation safe before the commencement of repair work.
3. POA Structural Repairs by Qualified Tradesperson
* Coordinated with a professional carpenter to arrange repairs to the damaged POA mounting structure.
* Allowed the necessary timber and gutter repairs to be completed before proceeding with the electrical reconnection.
4. Overhead Service Replacement & Reconnection
* Removed and replaced the existing overhead service mains with new compliant service cables.
* Reinstalled and securely connected the overhead service to the repaired Point of Attachment.
* Completed the necessary Level 2 ASP service reconnection works to restore the property’s electricity supply.
5. Electrical Testing & Defect Rectification
* Carried out the required electrical safety inspections, testing and verification following completion of the works.
* Completed the electrical rectification works associated with the Ausgrid defect notice in accordance with applicable Australian Standards and network requirements.
Chapman Ave Beecroft
Project details
Scope of Work:
1. Consumer Mains Replacement & Three-Phase Power Upgrade
* Remove and replace the existing consumer mains with new appropriately sized three-phase cables.
* Upgrade the existing two-phase electrical supply to a three-phase power supply.
* Complete all necessary cable connections and associated electrical works to accommodate the upgraded three-phase system.
2. Complete Main Switchboard Replacement & Upgrade
* Remove the existing main switchboard and install a new three-phase main switchboard.
* Completely upgrade the existing distribution board, including main switches, protective devices, internal wiring and associated electrical components.
* Reorganise and reconfigure the electrical circuits to suit the new three-phase supply.
3. Complete Circuit Breaker to RCBO Upgrade
* Remove all existing circuit breakers (CBs) from the original distribution board.
* Replace all existing CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all existing electrical circuits.
4. New Earth Electrode Installation
* Supply and install a new earth electrode (earth stake) to upgrade the existing earthing system.
* Complete the necessary earthing connections and ensure compliance with applicable electrical safety requirements.
5. Electrical Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and commissioning.
* Verify the three-phase supply, protective devices and earthing system in accordance with relevant Australian Standards and network service provider requirements.
Greenway Dr Pymble
Project details
Scope of Work:
1. Consumer Mains Replacement
* Remove and replace the existing consumer mains with new appropriately sized cables to meet current electrical requirements.
* Complete all necessary cable connections and associated electrical works.
2. Main Switchboard Replacement & Distribution Board Upgrade
* Remove the existing main switchboard enclosure and install a new compliant switchboard.
* Upgrade the entire distribution board, including main switches, protective devices, internal wiring and associated electrical components.
* Reorganise and reconfigure the existing circuits to improve electrical safety and reliability.
3. Smart Electricity Meter Installation
* Replace the existing electricity meter with a new smart meter.
* Complete the necessary metering upgrades and connections in accordance with electricity network and metering provider requirements.
4. Complete Load Circuit RCBO Upgrade
* Remove all existing circuit breakers (CBs) protecting the load circuits.
* Replace all existing load circuit CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all load circuits.
5. Electrical Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and commissioning.
* Ensure the upgraded electrical installation complies with relevant Australian Standards and electricity network requirements.
The Esplanade Frenchs Forest
Project details
Scope of Work:
1. Consumer Mains Replacement
* Remove and replace the existing consumer mains with new appropriately sized cables to meet current electrical requirements.
* Complete all necessary cable connections and associated electrical works.
2. Main Switchboard Replacement & Distribution Board Upgrade
* Remove the existing main switchboard and install a new compliant switchboard enclosure.
* Upgrade the entire distribution board, including main switches, protective devices, internal wiring and associated electrical components.
* Reorganise and reconfigure the existing electrical circuits to improve safety and reliability.
3. Smart Electricity Meter Installation
* Replace the existing electricity meter with a new smart meter.
* Complete the necessary metering connections and upgrades in accordance with relevant electricity network and metering provider requirements.
4. Complete Load Circuit RCBO Upgrade
* Remove all existing circuit breakers (CBs) protecting the load circuits.
* Replace all load circuit CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all existing load circuits.
5. SolaX 51.2kWh Battery Energy Storage System Installation
* Supply and install a SolaX 51.2kWh battery energy storage system (BESS).
* Complete all necessary battery wiring, electrical connections and associated protection requirements.
* Integrate and configure the battery system with the property’s electrical installation and compatible inverter system.
* Perform battery system setup, testing and commissioning to ensure safe and reliable operation.
6. Electrical Testing & Commissioning
* Carry out all necessary electrical safety testing, inspections and system commissioning.
* Verify the switchboard, RCBO protection, metering arrangement and battery installation in accordance with applicable Australian Standards and network requirements.
Yanilla Ave Wahroonga
Project details
Scope of Work:
1. Consumer Mains Replacement
* Remove and replace the existing consumer mains with new appropriately sized three-phase cables.
* Complete all necessary cable connections and associated electrical works to accommodate the upgraded three-phase power supply.
2. Main Switchboard Replacement & Distribution Board Upgrade
* Remove the existing main switchboard and install a new compliant switchboard enclosure.
* Upgrade the entire distribution board, including main switches, protective devices, internal wiring and associated electrical components.
* Reorganise and reconfigure the existing electrical circuits to suit the new three-phase distribution system.
3. Electricity Meter Consolidation & Three-Phase Meter Installation
* Decommission and remove the three existing single-phase electricity meters.
* Arrange for the installation of one new three-phase electricity meter to replace the three separate single-phase meters.
* Reconfigure and consolidate the existing electrical supplies into a single three-phase metering arrangement.
* Complete all necessary metering connections and associated electrical modifications.
4. Complete Circuit Breaker to RCBO Upgrade
* Remove all existing circuit breakers (CBs) from the distribution board.
* Replace all existing CBs with the pre-provided RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all existing electrical circuits.
5. New Earth Electrode Installation
* Supply and install a new earth electrode (earth stake) to upgrade the existing earthing system.
* Complete all necessary earthing connections and verify the integrity of the earthing system.
6. Electrical Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and commissioning.
* Ensure the upgraded installation complies with relevant Australian Standards and electricity network requirements.
Carlisle Cr Beecroft
Project details
Scope of Work:
1. Consumer Mains Replacement
* The property was equipped with a low-voltage battery energy storage system, but the existing consumer mains cables were undersized for the electrical installation requirements.
* Remove and replace the existing consumer mains with new appropriately sized cables to accommodate the battery system and electrical load requirements.
* Complete all necessary cable connections and associated electrical works.
2. Meter Panel Replacement & Upgrade
* Remove and replace the existing electricity meter mounting panel with a new compliant meter panel.
* Upgrade and reorganise the associated metering wiring and electrical components to accommodate the upgraded consumer mains and battery system.
3. Main Switch Upgrade
* Remove and replace the existing main switch with a new appropriately rated main switch.
* Upgrade the associated wiring and connections to suit the updated electrical installation.
4. Circuit Breaker to RCBO Upgrade
* Remove the existing circuit breakers (CBs) and replace them with RCBOs.
* Provide overload, short-circuit and residual current protection for the upgraded circuits.
* Reconnect and clearly label the electrical circuits.
5. Electrical Testing & Commissioning
* Carry out all necessary electrical safety inspections, testing and commissioning.
* Verify the upgraded consumer mains, main switch, RCBO protection and associated electrical connections in accordance with relevant Australian Standards and network requirements.
Rosehill St Parramatta
Project details
Scope of Work:
1. Consumer Mains Replacement
* The existing consumer mains cables were undersized and required upgrading.
* Remove and replace the existing consumer mains with new appropriately sized cables to accommodate the property’s electrical requirements and new solar battery system.
* Complete all necessary cable connections and associated electrical works.
2. Main Switchboard Relocation & Complete Upgrade
* Disconnect and remove the existing main switchboard and distribution board from their original location.
* Relocate the electrical distribution system to a new, suitable position.
* Supply and install a new main switchboard enclosure and distribution board.
* Upgrade and reorganise all associated internal wiring, main switches and electrical components.
3. Smart Electricity Meter Installation
* Replace the existing electricity meter with a new smart meter.
* Complete the necessary metering connections and modifications to accommodate the upgraded electrical installation and solar battery system.
4. Complete Circuit Breaker to RCBO Upgrade
* Remove all existing circuit breakers (CBs) from the original distribution board.
* Replace all existing load circuit CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all existing electrical circuits within the new switchboard.
5. New Earth Electrode Installation
* Supply and install a new earth electrode (earth stake) to upgrade the existing earthing system.
* Complete the necessary earthing connections and verify the integrity and safety of the earthing system.
6. Solar PV & Battery Energy Storage System Installation
* Supply and install a new solar photovoltaic (PV) and battery energy storage system (BESS).
* Install the required solar panels, inverter, battery units, electrical cabling and associated protection devices.
* Integrate the solar and battery system with the upgraded main switchboard.
* Configure and commission the system to enable solar energy generation, battery storage and efficient energy management.
7. Electrical Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and system commissioning.
* Verify the consumer mains, switchboard, RCBO protection, earthing system and solar battery installation in accordance with relevant Australian Standards and electricity network requirements.
Northcote Ave Killara
Project details
Scope of Work:
1. Main Switchboard Replacement & Distribution Board Upgrade
* Remove and replace the existing main switchboard with a new compliant switchboard enclosure.
* Upgrade the entire distribution board, including main switches, protective devices, internal wiring and associated electrical components.
* Reconfigure the electrical distribution system to accommodate the new SolaX inverter and battery storage system.
2. Existing Electrical Wiring Reorganisation
* Inspect, identify and reorganise the existing electrical wiring within the switchboard.
* Reroute and neatly arrange the existing cables to improve cable management, circuit identification and overall electrical safety.
* Reconnect and clearly label all existing electrical circuits.
3. Complete Circuit Breaker to RCBO Upgrade
* Remove all existing circuit breakers (CBs) from the distribution board.
* Replace all existing load circuit CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconfigure and reconnect all relevant circuits within the upgraded switchboard.
4. SolaX 51.2kWh Battery & Inverter Installation
* Supply and install a SolaX 51.2kWh battery energy storage system (BESS) and a compatible SolaX hybrid inverter.
* Complete all necessary battery and inverter wiring, electrical connections and protection arrangements.
* Configure the inverter and battery system for efficient solar energy storage and management.
5. Existing Solar PV System Integration
* Reconfigure and reconnect the existing solar PV system to the new SolaX hybrid inverter and battery storage system.
* Complete all necessary solar DC wiring modifications and system connections.
* Integrate the existing solar panels with the new inverter and battery to enable solar generation, battery charging and energy management.
6. Electrical Testing & Commissioning
* Carry out all necessary electrical testing, safety inspections and system commissioning.
* Verify the upgraded switchboard, RCBO protection, inverter, battery storage system and existing solar PV integration in accordance with relevant Australian Standards and electricity network requirements.
Daffodil Cr Kellyville
Project details
Scope of Work:
1. Main Switchboard Replacement & Upgrade
* The existing switchboard had insufficient space to accommodate the additional electrical components required for the new SolaX 51.2kWh battery storage system.
* Remove the existing switchboard enclosure and install a new, larger switchboard to provide adequate space for the battery system connections and associated electrical components.
2. Existing Electrical Wiring Reorganisation
* Inspect, identify and reorganise the existing electrical wiring within the switchboard.
* Reroute and neatly arrange the existing cables to improve cable management, circuit layout and electrical safety.
* Ensure sufficient space for electrical components and future maintenance.
3. Distribution Board Reinstallation & Reconfiguration
* Reinstall and reconfigure the distribution board within the new switchboard enclosure.
* Reconnect all existing electrical circuits and reorganise the associated protective devices and internal wiring.
* Clearly label all electrical circuits and components.
4. SolaX 51.2kWh Battery Energy Storage System Installation
* Supply and install a SolaX 51.2kWh battery energy storage system (BESS).
* Complete all necessary battery cabling, electrical connections and associated protection arrangements.
* Integrate the battery storage system with the upgraded switchboard and compatible inverter.
* Complete system configuration, testing and commissioning.
5. Electrical Testing & Commissioning
* Carry out all necessary electrical safety inspections, testing and commissioning in accordance with relevant Australian Standards and electricity network requirements.
Crana Ave East Lindfield
Project details
Scope of Work:
1. Single-Phase to Three-Phase Power Upgrade & Consumer Mains Replacement
* Upgrade the existing single-phase electrical supply to a three-phase power supply.
* Remove and replace the existing consumer mains with new appropriately sized three-phase cables.
* Complete all necessary electrical connections and associated Level 2 ASP works.
2. Main Switchboard Replacement & Upgrade
* Remove the existing main switchboard and install a new three-phase switchboard enclosure.
* Supply and install a new distribution board, including main switches, protective devices and associated electrical components.
* Upgrade and reorganise the internal wiring to accommodate the new three-phase supply, solar PV system and battery storage system.
3. Three-Phase Smart Meter Installation
* Replace the existing single-phase electricity meter with a new three-phase smart meter.
* Complete the necessary metering connections and modifications in accordance with electricity network and metering provider requirements.
4. Complete Load Circuit RCBO Upgrade
* Remove all existing circuit breakers (CBs) protecting the load circuits.
* Replace all load circuit CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all electrical circuits within the new distribution board.
5. 13.3kW Rooftop Solar PV System Installation
* Supply and install a 13.3kW rooftop solar photovoltaic (PV) system.
* Install solar panels, roof mounting systems, DC cabling and associated electrical protection devices.
* Complete all necessary solar panel connections and wiring.
6. 15kW Three-Phase Hybrid Inverter Installation
* Supply and install a 15kW three-phase hybrid inverter.
* Connect and configure the inverter with the solar PV system, three-phase electrical supply and battery storage system.
* Complete all necessary AC/DC connections and system configuration.
7. CQ6-L8 Series 47.92kWh Battery Energy Storage System Installation
* Supply and install a CQ6-L8 series battery energy storage system with a total capacity of 47.92kWh.
* Complete all necessary battery cabling, electrical connections and associated protection arrangements.
* Integrate the battery system with the hybrid inverter to enable solar energy storage and energy management.
* Configure and commission the battery storage system.
8. Electrical Testing & Commissioning
* Carry out all necessary electrical safety inspections, testing and system commissioning.
* Verify the upgraded three-phase supply, consumer mains, switchboard, RCBO protection, solar PV system, inverter and battery installation.
* Ensure all works comply with applicable Australian Standards and electricity network requirements.
McBurney Rd Cabramatta
Project details
Scope of Work:
1. Private Power Pole Installation
* Supply and install a new private power pole to establish a suitable electricity supply connection for the construction site.
* Complete all necessary pole installation and associated electrical works.
2. Overhead Service Installation
* Supply and install new overhead service mains from the network service pole to the new private power pole.
* Complete all necessary Level 2 ASP overhead service connection works.
3. Consumer Mains Installation
* Supply and install new appropriately sized consumer mains cables from the private power pole to the temporary construction switchboard.
* Complete all necessary cable connections and associated electrical wiring.
4. Temporary Construction Switchboard Installation
* Supply and install a new temporary builder’s supply switchboard and distribution board.
* Install the required main switch, circuit protection devices, RCBOs and associated electrical components.
* Establish a safe and reliable temporary electricity supply for construction activities.
5. Electrical Testing & Commissioning
* Carry out all necessary electrical safety inspections, testing and commissioning.
* Ensure the installation complies with relevant Australian Standards and electricity network requirements.
Osborne Rd Greenwich
Project details
Scope of Work:
1. Consumer Mains Replacement & Upgrade
* Engaged by the builder to carry out electrical upgrade works as part of the residential renovation project.
* Remove and replace the existing consumer mains with new appropriately sized cables to accommodate the property’s updated electrical requirements.
* Complete all necessary cable connections and associated Level 2 ASP electrical works.
2. Main Switchboard Replacement & Upgrade
* Remove the existing main switchboard and install a new compliant switchboard enclosure.
* Upgrade and reorganise the associated internal wiring, main switches, protective devices and electrical components as required.
* Ensure the upgraded switchboard is suitable for the renovated property’s electrical installation.
3. Smart Electricity Meter Installation
* Arrange for the replacement of the existing electricity meter with a new smart meter.
* Complete the necessary metering connections and associated electrical modifications in accordance with electricity network and metering provider requirements.
4. Electrical Testing & Commissioning
* Carry out all necessary electrical safety inspections, testing and commissioning.
* Ensure the upgraded electrical installation complies with applicable Australian Standards and electricity network requirements.
O‘Keefe Cr Eastwood
Project details
Scope of Work:
1. Private Power Pole Installation
* Engaged by the builder to carry out Level 2 ASP electrical connection works for the property.
* Installed a new private power pole during the early stage of construction, prior to the commencement of brickwork.
* Prepared the private power pole for the future overhead service connection and underground consumer mains.
2. Overhead Service Installation & Connection
* Returned to the site at a later stage of construction to install the new overhead service mains crossing the street.
* Connected the overhead service from the network service pole to the newly installed private power pole.
* Completed the necessary Level 2 ASP overhead service connection works.
3. Underground Consumer Mains Installation & Termination
* The underground consumer mains had been previously installed by the on-site electrician, with the cable ends brought up from underground near the base of the private power pole.
* Routed the existing consumer mains into the private power pole and pulled the cables internally up to the top of the pole.
* Secured and terminated the consumer mains at the overhead service connection point.
* Completed all necessary cable connections and associated electrical works.
4. New Electricity Meter Installation & Power Connection
* Completed the necessary metering connections at the main switchboard and arranged for the installation of a new electricity meter.
* Connected and energised the electrical installation to establish the property’s electricity supply.
5. Electrical Testing, Inspection & Compliance
* Carried out all required electrical safety inspections and testing.
* Verified the overhead service connection, consumer mains termination, metering connections and electrical installation.
* Completed the relevant compliance documentation and ensured the work met applicable Australian Standards and electricity network requirements.
Lane Cove Rd North Ryde
Project details
Scope of Work:
1. Single-Phase to Three-Phase Power Upgrade
* Upgrade the existing single-phase electrical supply to a three-phase power supply.
* Complete all necessary Level 2 ASP service connection works to accommodate the new three-phase electrical system.
2. Overhead Service & Consumer Mains Replacement
* Disconnect and remove the existing single-phase overhead service mains.
* Supply and install new three-phase overhead service mains.
* Remove and replace the existing consumer mains with appropriately sized three-phase cables.
* Complete all necessary service connections and associated electrical works.
3. Main Switchboard Replacement & Distribution Board Upgrade
* Remove the existing main switchboard and install a new three-phase switchboard enclosure.
* Supply and install a new distribution board, including main switches, protective devices and associated electrical components.
* Reorganise and upgrade the internal wiring to accommodate the new three-phase supply, solar PV system and battery storage system.
4. New Three-Phase Electricity Meter Installation
* Replace the existing single-phase electricity meter with a new three-phase electricity meter through the authorised metering arrangements.
* Complete the necessary metering connections and associated electrical modifications.
5. Complete Load Circuit RCBO Upgrade
* Remove all existing circuit breakers (CBs) protecting the load circuits.
* Replace all existing load circuit CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all existing electrical circuits within the new distribution board.
6. 11.4kW Rooftop Solar PV System Installation
* Supply and install an 11.4kW rooftop solar photovoltaic (PV) system.
* Install solar panels, mounting systems, DC cabling and associated electrical protection devices.
* Complete all necessary solar panel wiring and electrical connections.
7. FoxESS 15kW Three-Phase Hybrid Inverter Installation
* Supply and install a FoxESS 15kW three-phase hybrid inverter.
* Connect and configure the inverter with the solar PV system, three-phase electrical supply and FoxESS battery storage system.
* Complete all necessary AC/DC electrical connections and system configuration.
8. FoxESS 41.94kWh Battery Energy Storage System Installation
* Supply and install a FoxESS 41.94kWh battery energy storage system (BESS).
* Complete all necessary battery cabling, electrical connections and associated protection arrangements.
* Integrate the battery with the FoxESS hybrid inverter to enable solar energy storage and energy management.
* Configure and commission the battery storage system.
9. Electrical Testing, Commissioning & Compliance
* Carry out all necessary electrical safety inspections, testing and system commissioning.
* Verify the upgraded three-phase supply, overhead service, consumer mains, switchboard, RCBO protection, solar PV system, inverter and battery installation.
* Complete the required electrical compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Harley Cr Eastwood
Project details
Scope of Work:
1. Electrical Service Disconnection & Make-Safe
* Safely disconnect and isolate the existing electrical supply before commencing the upgrade works.
* Ensure the electrical installation is safe for the required modifications.
2. Consumer Mains Replacement & Upgrade
* Remove and replace the existing consumer mains with new appropriately sized cables.
* Upgrade the consumer mains to accommodate the property’s electrical requirements and planned future battery energy storage system.
* Complete all necessary cable connections and associated electrical works.
3. Switchboard & Electrical Components Upgrade
* Remove and replace the existing distribution board with a new upgraded board.
* Replace the existing service fuse and associated electrical components as required.
* Upgrade and reorganise the internal wiring, protective devices and associated connections.
* Prepare the electrical installation for the future connection of a battery energy storage system.
4. Electrical Service Reconnection & Power Restoration
* Reconnect the electrical supply following completion of the upgrade works.
* Restore power to the property and verify normal operation.
5. Electrical Testing & Compliance
* Carry out all necessary electrical safety inspections and testing.
* Verify the upgraded consumer mains, switchboard, service fuse and associated electrical connections.
* Complete the required compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Curtin Ave North Wahroonga
Project details
Scope of Work:
1. Electrical Service Disconnection & Reconnection
* Safely disconnect and isolate the existing electrical supply before commencing the upgrade works.
* Complete all necessary Level 2 ASP electrical disconnection and reconnection works.
* Restore power to the property following completion of the electrical upgrades and safety testing.
2. Consumer Mains Replacement
* Remove and replace the existing consumer mains with new appropriately sized cables to accommodate the upgraded electrical installation.
* Complete all necessary cable connections and associated electrical works.
3. Main Switchboard Panel Replacement & Wiring Reorganisation
* Remove the existing switchboard panel and install a new compliant distribution panel.
* Inspect, identify and reorganise the existing electrical wiring.
* Reroute and neatly arrange the internal cables to improve cable management, circuit identification and electrical safety.
* Reconnect and clearly label all existing electrical circuits.
4. Main Switch & Ceramic Fuse Upgrade
* Remove and replace the existing main switch with a new appropriately rated main switch.
* Remove the outdated ceramic fuse holders and associated components.
* Replace the old ceramic fuse protection devices with modern, compliant circuit protection devices, including RCBOs where required.
* Upgrade the associated wiring and electrical accessories to meet applicable Australian electrical safety requirements.
5. 14.25kW Rooftop Solar PV System Installation
* Supply and install a 14.25kW rooftop solar photovoltaic (PV) system.
* Install solar panels, roof mounting systems, DC cabling and associated electrical protection devices.
* Complete all necessary solar panel wiring and electrical connections.
6. 15kW Hybrid Inverter Installation
* Supply and install a 15kW hybrid inverter.
* Connect and configure the inverter with the solar PV system, electrical supply and battery storage system.
* Complete all necessary AC/DC wiring, protection arrangements and system configuration.
7. 47.92kWh Battery Energy Storage System Installation
* Supply and install a 47.92kWh battery energy storage system (BESS).
* Complete all necessary battery cabling, electrical connections and associated protection devices.
* Integrate the battery system with the hybrid inverter to enable solar energy storage and energy management.
* Configure and commission the battery storage system.
8. Electrical Testing, Commissioning & Compliance
* Carry out all necessary electrical safety inspections, testing and system commissioning.
* Verify the upgraded consumer mains, switchboard, main switch, circuit protection devices, solar PV system, inverter and battery installation.
* Complete the required compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Horace St St Ives
Project details
Scope of Work:
1. Level 2 ASP Works – Residential Renovation
* Engaged by the builder to carry out Level 2 ASP electrical upgrade works as part of the residential renovation project.
* Upgrade the property’s existing single-phase electricity supply to a three-phase supply.
* Convert the existing overhead service connection to a new underground electrical supply arrangement.
2. Existing Overhead Service Disconnection
* Safely disconnect and remove the existing overhead service connection.
* Complete all necessary electrical isolation and make-safe procedures before commencing the underground service upgrade.
3. Underground Service Installation – Network Service Pole to Private Pillar
* Install new three-phase underground service cables from the network service pole to the private pillar.
* Complete all necessary underground cable connections, terminations and associated Level 2 ASP works.
* Establish a new underground service connection to replace the existing overhead supply arrangement.
4. Underground Consumer Mains Installation
* Install new appropriately sized three-phase underground consumer mains from the private pillar to the Main Switchboard (MSB).
* Complete all necessary cable routing, connections and terminations.
* Configure the electrical supply to accommodate the new three-phase distribution system.
5. Main Switchboard Replacement & Distribution Board Upgrade
* Disconnect and remove the existing main switchboard and distribution panel.
* Supply and install a new three-phase main switchboard enclosure and distribution board.
* Upgrade the associated main switches, protective devices, internal wiring and electrical components.
* Reorganise and reconnect the existing electrical circuits to suit the upgraded three-phase supply.
6. New Three-Phase Smart Meter Installation
* Arrange for the installation of a new three-phase smart electricity meter.
* Complete the required metering panel upgrades, wiring modifications and connections.
* Configure the new metering arrangement to accommodate the upgraded three-phase electricity supply.
7. Electrical Connection, Testing & Compliance
* Complete the necessary electrical service connections and energisation.
* Carry out all required electrical safety inspections, testing and commissioning.
* Verify the underground service connection, consumer mains, main switchboard and three-phase metering arrangement.
* Complete the relevant electrical compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Neville St Ryde
Project details
Scope of Work:
1. Site Inspection & Electrical Service Disconnection
* Engaged by the builder to carry out Level 2 ASP electrical works at the construction site.
* The existing temporary construction switchboard and private power pole were struck by a heavy vehicle, causing the installation to lean and creating potential electrical safety hazards.
* Safely disconnected and isolated the existing electrical supply before commencing the replacement works.
2. Temporary Switchboard & Damaged Pole Removal
* Disconnect and dismantle the existing temporary construction switchboard and associated electrical components.
* Remove the damaged and leaning private power pole.
* Make the site safe for the installation of the replacement power pole.
3. New Private Power Pole Installation
* Supply and install a new private power pole to replace the damaged pole.
* Securely install the new pole to accommodate the overhead service connection and underground consumer mains.
4. Overhead Service Reinstallation
* Reinstall the overhead service mains crossing the street from the network service pole to the new private power pole.
* Complete all necessary overhead service connections and associated Level 2 ASP works.
5. Underground Consumer Mains Connection
* Connect the existing underground consumer mains to the new private power pole.
* Complete the necessary cable routing, termination and electrical connections to establish the supply to the building’s main switchboard.
6. Electricity Meter Relocation to Main Switchboard
* Relocate the electricity metering arrangement from the temporary construction supply to the permanent main switchboard mounted on the external wall of the building.
* Arrange for the installation and connection of the electricity meter within the new main switchboard.
* Complete all necessary metering connections and associated electrical modifications.
7. Electrical Service Reconnection & Power Restoration
* Reconnect and energise the electrical supply following completion of the installation works.
* Restore electricity supply to the property through the permanent main switchboard.
8. Electrical Testing, Commissioning & Compliance
* Carry out all necessary electrical safety inspections, testing and commissioning.
* Verify the overhead service connection, private power pole, underground consumer mains and metering installation.
* Complete the relevant electrical compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Neville St Ryde
Project details
Scope of Work:
1. Private Power Pole Installation
* Engaged by the builder to carry out Level 2 ASP electrical connection works for the property.
* Supply and install a new private power pole to establish a suitable electricity supply connection.
* Prepare the pole for overhead service and underground consumer mains connections.
2. Overhead Service Installation
* Supply and install new overhead service mains crossing the street from the network service pole to the new private power pole.
* Complete all necessary Level 2 ASP overhead service connection works.
3. Underground Consumer Mains Connection
* Connect the existing underground consumer mains to the new private power pole.
* Route the consumer mains through the private power pole to the overhead service connection point.
* Complete all necessary cable terminations and electrical connections.
4. Electricity Meter Installation
* Arrange for the installation of a new electricity meter at the main switchboard.
* Complete the necessary metering connections and associated electrical works.
5. Power Supply Connection & Energisation
* Complete the final electrical service connections.
* Energise the electrical installation and establish power supply to the property.
6. Electrical Testing & Compliance
* Carry out all necessary electrical safety inspections and testing.
* Verify the private power pole, overhead service, underground consumer mains and metering connections.
* Complete the required compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Redfield Rd East Killara
Project details
Scope of Work:
1. Two-Phase to Three-Phase Power Upgrade
* Upgrade the existing two-phase electrical supply to a three-phase power supply.
* Complete all necessary Level 2 ASP electrical connection works to accommodate the upgraded three-phase system.
2. Consumer Mains Replacement
* Remove and replace the existing consumer mains with new appropriately sized three-phase cables.
* Complete all necessary cable connections and associated electrical modifications to support the upgraded three-phase power supply.
3. Main Switchboard Panel Replacement & Upgrade
* Remove the existing main switchboard panel and install a new three-phase distribution panel.
* Replace and upgrade the associated main switches, protective devices, wiring and electrical components as required.
* Reorganise the internal wiring and electrical connections to improve safety, reliability and circuit identification.
4. Indoor Sub-Board Circuit Breaker to RCBO Upgrade
* Remove all existing circuit breakers (CBs) from the indoor sub-distribution board.
* Replace all existing load circuit CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all circuits within the existing sub-board.
5. New Earth Electrode Installation
* Supply and install a new earth electrode (earth stake) to upgrade the existing earthing system.
* Complete the necessary earthing connections and verify the integrity of the earthing system.
6. Electrical Testing, Commissioning & Compliance
* Carry out all necessary electrical safety inspections, testing and commissioning.
* Verify the upgraded three-phase supply, consumer mains, main switchboard, RCBO protection and earthing system.
* Complete the required electrical compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Rosanna Cl Willoughby
Project details
Scope of Work:
1. Single-Phase to Three-Phase Power Upgrade & Service Disconnection
* Upgrade the existing single-phase electricity supply to a three-phase power supply.
* Safely disconnect and isolate the existing electrical supply before commencing the upgrade works.
* Complete the necessary Level 2 ASP disconnection works.
2. Underground Consumer Mains Replacement
* Remove and replace the existing underground consumer mains between the electricity supply pillar and the main switchboard (MSB).
* Install new appropriately sized three-phase consumer mains cables to accommodate the upgraded electrical supply.
* Complete all necessary cable terminations and electrical connections at both ends.
3. Three-Phase Smart Meter & Main Switch Installation
* Arrange for the installation of a new three-phase smart electricity meter to replace the existing single-phase metering arrangement.
* Replace and upgrade the existing main switch with a new appropriately rated three-phase main switch.
* Complete the associated metering and electrical connections.
4. Switchboard Reconfiguration & Electrical Distribution Upgrade
* Reconfigure the existing switchboard and associated internal wiring to accommodate the new three-phase supply.
* Reorganise and redistribute the existing electrical circuits across the three phases as appropriate.
* Upgrade the necessary electrical connections and associated components.
5. Power Supply Reconnection & Energisation
* Complete the required Level 2 ASP service reconnection works.
* Reconnect and energise the upgraded three-phase electrical supply.
* Restore electricity supply to the property.
6. Electrical Testing, Commissioning & Compliance
* Carry out all necessary electrical safety inspections, testing and commissioning.
* Verify the underground consumer mains, three-phase metering, main switch, phase distribution and electrical connections.
* Complete the required electrical compliance documentation in accordance with applicable Australian Standards and network service provider requirements.
Curtin Ave North Wahroonga
Project details
Scope of Work:
1. Electrical Service Disconnection & Make-Safe
* Safely disconnect and isolate the existing electrical supply before commencing the upgrade works.
* Complete all necessary Level 2 ASP disconnection and safety procedures.
2. Switchboard Panel Replacement & Upgrade
* Remove the existing switchboard panel and install a new compliant distribution panel.
* Upgrade and reorganise the associated internal wiring, electrical connections and components.
3. Fuse Replacement & Upgrade
* Remove and replace the existing fuse with a new appropriately rated fuse and associated components.
* Complete the necessary electrical connections and protection upgrades.
4. Complete Indoor Ceramic Fuse & Circuit Breaker to RCBO Upgrade
* Remove all existing ceramic rewirable fuses and circuit breakers (CBs) from the indoor distribution board.
* Replace all existing load circuit protection devices with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all electrical circuits.
5. Electrical Testing & Safety Inspection
* Carry out all necessary electrical safety inspections and testing.
* Verify the upgraded switchboard panel, fuse protection, RCBO operation and associated electrical connections.
6. Electrical Service Reconnection & Power Restoration
* Complete the necessary Level 2 ASP service reconnection works following successful safety testing.
* Reconnect and energise the electrical installation.
* Restore normal electricity supply to the property.
Toolang Rd St Ives
Project details
Scope of Work:
1. Existing Electrical Service Disconnection
* Engaged by the builder to carry out Level 2 ASP electrical works as part of a residential renovation project.
* Safely disconnect and isolate the existing electrical supply to the property before commencing construction and electrical modifications.
* Complete all necessary electrical disconnection and make-safe procedures.
2. Private Power Pole Installation
* Supply and install a new private power pole to establish a suitable electricity supply connection for the renovation site.
* Encountered extensive rock and hard ground conditions during excavation, requiring additional excavation work and preparation for the pole foundation.
* Complete the necessary groundwork and securely install the new private power pole.
3. Overhead Service Installation
* Supply and install new overhead service mains from the network service pole to the newly installed private power pole.
* Complete all necessary Level 2 ASP overhead service connections and associated electrical works.
4. Consumer Mains Installation
* Supply and install new appropriately sized consumer mains cables from the private power pole to the temporary construction switchboard.
* Complete all necessary cable routing, terminations and electrical connections.
5. Temporary Builder’s Supply Installation
* Supply and install a new temporary construction switchboard and distribution board.
* Install the required main switch, circuit protection devices, RCBOs and associated electrical components.
* Establish a suitable temporary power supply for the residential renovation works.
6. Electrical Testing, Inspection & Power Reconnection
* Carry out all necessary electrical safety inspections and testing.
* Verify the private power pole, overhead service, consumer mains and temporary switchboard installation.
* Complete the required Level 2 ASP service reconnection and energisation works.
* Restore electricity supply to the construction site in accordance with applicable Australian Standards and electricity network requirements.
Mawson St St Ives
Project details
Scope of Work:
1. Existing Electrical Service Disconnection
* Carry out Level 2 ASP electrical works as part of the residential demolition and rebuilding project.
* Safely disconnect and isolate the existing electricity supply before commencing the new underground service installation.
* Complete all necessary electrical disconnection and make-safe procedures.
2. Private Service Pillar Installation
* Supply and install a new private electrical service pillar to establish a new underground power supply connection for the property.
* Prepare and securely install the pillar in a suitable location to accommodate the underground electrical service.
3. Trenching & Underground Cable Route Preparation
* Carry out excavation and trenching works between the private service pillar and the network service pole.
* Prepare the underground cable route, including the necessary conduits and associated underground electrical infrastructure.
* Ensure the trenching and cable installation meet applicable electrical and network requirements.
4. Underground Service Cable Installation
* Install new underground electrical service cables from the private service pillar to the network service pole, replacing the previous supply arrangement.
* Complete the necessary cable routing, protection and terminations.
* Carry out the required Level 2 ASP underground service connection works.
5. Electrical Testing, Inspection & Compliance
* Carry out the necessary electrical safety inspections and testing.
* Verify the private service pillar, underground cable installation and associated electrical connections.
* Complete the relevant compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Douglas St St Ives
Project details
Scope of Work:
1. Electrical Service Disconnection
* Engaged by the builder to carry out Level 2 ASP electrical works for the construction project.
* Safely disconnect and isolate the existing electrical supply before commencing the installation and upgrade works.
2. Overhead Service Upgrade
* Upgrade the existing overhead service mains to accommodate the new three-phase electrical supply.
* Install and connect the upgraded overhead service cables.
* Complete all necessary Level 2 ASP service connection works.
3. Consumer Mains Installation
* Supply and install new appropriately sized three-phase consumer mains cables.
* Complete all necessary cable routing, terminations and electrical connections to the temporary construction switchboard.
4. Temporary Construction Switchboard & Distribution Board Installation
* Supply and install a new temporary construction switchboard and distribution board.
* Install the required main switch, circuit breakers, RCBOs and associated electrical components.
* Complete the internal wiring and circuit configuration to establish a temporary three-phase power supply for construction activities.
5. Three-Phase Smart Meter Installation
* Arrange for the installation of a new three-phase smart electricity meter.
* Complete the necessary metering connections and associated electrical modifications.
6. Earth Electrode Installation
* Supply and install a new earth electrode (earth stake).
* Complete the necessary earthing connections for the temporary electrical installation.
7. Electrical Testing, Inspection & Power Connection
* Carry out all necessary electrical safety inspections and testing.
* Verify the overhead service, consumer mains, temporary switchboard, metering connections and earthing system.
* Reconnect and energise the electrical supply following successful testing.
* Complete the required compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Macquarie Dr Cherrybrook
Project details
Scope of Work:
1. Electrical Service Disconnection
* The customer required an electrical switchboard upgrade to accommodate a three-phase inverter for a planned solar PV and battery energy storage system.
* Safely disconnect and isolate the existing electrical supply before commencing the upgrade works.
2. Main Switchboard & Distribution Board Upgrade
* Upgrade and replace the existing distribution board with a new three-phase distribution panel.
* Reorganise and upgrade the associated internal wiring, protective devices and electrical components.
* Prepare the electrical distribution system for the future installation of a three-phase solar and battery inverter.
3. Three-Phase Electricity Meter Installation
* Arrange for the installation of a new three-phase electricity meter.
* Complete the necessary metering connections and associated electrical modifications to accommodate the three-phase system.
4. Ceramic Fuse & Circuit Breaker to RCBO Upgrade
* Remove the existing outdated ceramic fuses and circuit breakers (CBs).
* Replace the old protective devices with modern RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all upgraded electrical circuits.
5. Electrical Testing, Inspection & Commissioning
* Carry out all necessary electrical safety inspections and testing.
* Verify the upgraded distribution board, three-phase metering arrangement and RCBO protection.
* Complete the required compliance checks and documentation in accordance with applicable Australian Standards and electricity network requirements.
Manor Rd Hornsby
Project details
Scope of Work:
1. Electrical Service Disconnection & Make-Safe
* Safely disconnect and isolate the existing electrical supply before commencing the upgrade works.
* Complete all necessary electrical disconnection and safety procedures.
2. Complete Main Switchboard Replacement
* Remove the existing main switchboard enclosure and all associated electrical equipment.
* Supply and install a new compliant main switchboard enclosure.
* Upgrade the associated electrical components and connections as required.
3. New Distribution Panel Installation
* Supply and install a new distribution panel within the switchboard.
* Reorganise and reconnect the existing electrical wiring and circuits.
* Install the required main switches, protective devices and associated electrical components.
4. New Earth Electrode Installation
* Supply and install a new earth electrode (earth stake) to upgrade the existing earthing system.
* Complete the necessary earthing connections and verify the integrity of the earthing system.
5. Complete Circuit Breaker to RCBO Upgrade
* Remove all existing circuit breakers (CBs).
* Replace all existing load circuit CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect and clearly label all electrical circuits.
6. Electrical Testing & Power Restoration
* Carry out all necessary electrical safety inspections and testing.
* Verify the new switchboard, distribution panel, RCBO protection and earthing system.
* Reconnect and restore the electrical supply following successful testing.
* Complete the required compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Koorong St Marsfield
Project details
Scope of Work:
1. Electrical Service Disconnection & Make-Safe
* Safely disconnect and isolate the existing electrical supply before commencing the upgrade works.
* Complete all necessary Level 2 ASP electrical disconnection and safety procedures.
2. Overhead Service Cable Replacement
* Remove and replace the existing overhead service cables with new appropriately rated cables.
* Complete all necessary overhead service connections and associated Level 2 ASP works.
3. Consumer Mains Replacement
* Remove and replace the existing consumer mains with new appropriately sized cables to meet the property’s electrical requirements.
* Complete all necessary cable routing, terminations and electrical connections.
4. Main Switchboard & Distribution Panel Upgrade
* Remove the existing distribution panel and associated outdated electrical components.
* Supply and install a new distribution panel with upgraded main switches, protective devices and electrical accessories.
* Reorganise and reconnect the existing electrical wiring and circuits.
5. New Electricity Meter Installation
* Arrange for the installation of a new electricity meter.
* Complete the necessary metering connections and associated electrical modifications in accordance with network and metering provider requirements.
6. Circuit Breaker to RCBO Upgrade
* Remove the existing circuit breakers (CBs).
* Install new RCBOs to provide overload, short-circuit and residual current protection for the relevant circuits.
* Reconnect and clearly label all upgraded electrical circuits.
7. Electrical Testing, Reconnection & Compliance
* Carry out all necessary electrical safety inspections and testing.
* Verify the overhead service, consumer mains, new distribution panel, metering connections and RCBO protection.
* Reconnect and restore the electrical supply following successful testing.
* Complete the required compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Valerie Ave Chatswood
Project details
Scope of Work:
1. Electrical Service Disconnection & Make-Safe
* Safely disconnect and isolate the existing electrical supply before commencing the upgrade works.
* Complete all necessary Level 2 ASP electrical disconnection and safety procedures.
2. Consumer Mains Replacement
* Remove and replace the existing consumer mains with new appropriately sized cables.
* Complete all necessary cable routing, terminations and electrical connections.
3. Main Switchboard Replacement & Upgrade
* Remove the existing switchboard enclosure, distribution panel and associated outdated electrical components.
* Supply and install a new main switchboard enclosure and distribution panel.
* Reorganise and reconnect the existing electrical wiring and circuits.
* Install the required main switches, protective devices and associated electrical components.
4. New Electricity Meter Installation
* Arrange for the installation of a new electricity meter within the upgraded switchboard.
* Complete the necessary metering connections and associated electrical modifications in accordance with network and metering provider requirements.
5. Circuit Breaker to RCBO Upgrade
* Remove the existing circuit breakers (CBs).
* Replace the existing load circuit CBs with new RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all electrical circuits.
6. Electrical Testing, Reconnection & Compliance
* Carry out all necessary electrical safety inspections and testing.
* Verify the consumer mains, new switchboard, distribution panel, meter connections and RCBO protection.
* Reconnect and restore the electricity supply following successful testing.
* Complete the required compliance documentation in accordance with applicable Australian Standards and electricity network requirements.
Lyon Cl Killara
Project details
Scope of Work:
1. Electrical Service Disconnection & Make-Safe
* Safely disconnect and isolate the existing electrical supply before commencing the upgrade works.
* Complete all necessary Level 2 ASP service disconnection and safety procedures.
2. Point of Attachment (POA) Relocation & Reconfiguration
* Relocate and reconfigure the existing overhead service Point of Attachment (POA) to a new suitable position.
* Reinstall and secure the overhead service connection at the new POA location.
* Complete the necessary service connection modifications and associated Level 2 ASP works.
3. Complete Main Switchboard Replacement & Upgrade
* Remove the existing main switchboard enclosure, distribution panel and associated outdated electrical components.
* Supply and install a new main switchboard enclosure and distribution panel.
* Upgrade and reorganise the internal wiring, main switches, protective devices and associated electrical components.
* Reconfigure the switchboard to accommodate the additional three-phase metering arrangement.
4. Separate Three-Phase Meter Installation for Granny Flat
* Arrange for the installation of an additional three-phase electricity meter dedicated to the granny flat.
* Separate and reconfigure the electrical supply and associated circuits for the granny flat.
* Establish independent electricity metering to allow the granny flat to monitor its electricity consumption and receive separate electricity bills from the main residence.
5. Complete Circuit Breaker to RCBO Upgrade
* Remove all existing load circuit breakers (CBs).
* Replace the existing CBs with individual RCBOs, providing overload, short-circuit and residual current protection.
* Reconnect, reorganise and clearly label all electrical circuits within the new distribution panel.
6. Electrical Testing, Service Reconnection & Compliance
* Carry out all necessary electrical safety inspections and testing.
* Verify the relocated POA, new switchboard, three-phase metering connections and RCBO protection.
* Reconnect and energise the electrical supply following successful testing.
* Complete the required compliance documentation in accordance with applicable Australian Standards and electricity network requirements.